Positions quoted in this Preliminary Notice reproduced below are referred to WGS84 or a compatible datum and may be plotted directly on this ENC. 
Some or all of the information contained in this Notice to Mariners may have been included on the ENCs affected.		
		
84(P)/25 INDONESIA  Sumatera Submarine cable.Works.		
Source: BW Digital & Telin		
		
	1.	The Nongsa-Changi submarine cable is being laid, joining the following positions:
		
		1 11' .63N.,104 06' .24E.

		1 12' .05N.,104 06' .70E.

		1 11' .93N.,104 07' .97E.

		1 12' .09N.,104 08' .33E.

		1 12' .63N.,104 08' .40E.

		1 12' .88N.,104 08' .77E.

		1 14' .10N.,104 09' .38E.

		1 14' .33N.,104 09' .70E.

		1 14' .34N.,104 10' .84E.

		1 14' .44N.,104 11' .40E.

		1 14' .64N.,104 11' .54E.

		1 15' .11N.,104 11' .50E.

		1 15' .34N.,104 11' .34E.

		1 15' .49N.,104 10' .98E.

		1 15' .57N.,104 10' .42E.

		1 15' .80N.,104 10' .14E.

		1 16' .62N.,104 07' .65E.

		1 17' .23N.,104 07' .53E.

		1 17' .54N.,104 07' .27E.
		
	2.	Charts will be updated when works are complete.
		
	3.	Mariners are advised to navigate with caution in the area.
		
		(WGS84 DATUM)